MICI-BID-CR-2017-0125
Reventazon Hydroelectric Power Project - Request IV
Country: Costa Rica
Reception date: August, 7 2017
Current Status: Closed
Requesters:
Three residents of San Joaquín de Siquirres, Costa Rica.
Summary of the Request
The Requesters allege harm to their property and economic loss, connected with the Reventazon Hydroelectric Power Project. Specifically, the Requesters claim that by expropriating part of the farm, the project cut-off the access to the aquifers that previously supplied water to the entire property and were used for different productive activities such as agriculture irrigation and water for their livestock. The above, per the Request, has caused significant economic losses and harm to the Requesters’ health.
This Request is linked to request MICI-IDB-CR-2016-0112, which was declared ineligible because the Requestors had not had prior contact with Management.
Recent actions
MICI conducted a monitoring mission to Costa Rica between July 29th and 31st, 2019, in which it was verified that all the agreements reached by the Parties were fulfilled. The Mechanism produced a Case Closure Report that was distributed for information to the Board of Executive Directors on September 9th, 2019, concluding MICI’s activities related to the case management.
Past actions
On August 10 2017, MICI notified the Requesters and Bank Management that the Request was registered.
On February 1, 2018, MICI determined that the Request was eligible because it met all the eligibility criteria established in the MICI Policy.
Regarding those operations that are relevant to the MICI process, this determination excludes transaction (CR-T1074) where exclusion 19 paragraph (f) applies because the Request was submitted 24 months after the last disbursement. Also, regarding the topics addressed in the Request, the access to drinking water was solved by Management, therefore it is excluded from the MICI process.
This determination of eligibility is not an assessment of the merits of the Request or of the issues contained therein. It also does not represent an approval to investigate the compliance or non-compliance of the Bank with its Relevant Operational Policies.
The Request was transferred to the Consultation Phase following the request of the Requesters to manage the case by both Phases of the MICI process.
As a result of a series of dialogues and analysis facilitated by MICI, on April 12, 2018, the Costa Rican Electricity Institute (ICE), the Requesters and IDB Group Management reached an agreement to provide a comprehensive solution that allows the restoration of access to water for animal troughs and irrigation of the Requester’s property. The Parties requested the confidentiality of the agreement.
On June 5, 2018, with the Board of Executive Directors's approval of the monitoring plan proposed by MICI, the monitoring stage of the agreements began.
Project Number:
Other related projects:
Environmental Category:
A
Project Name:
Power Sector Development Program 2012-2016 (Reventazon Hydroelectric Project)
Sector:
ENERGY
Project Type:
Loan Operation
IDB Financing:
USD 250,000,000
Registration Registered | Eligibility Eligible | Assessment | Consultation Process | Monitoring | Recommendation for a CR and ToRs | Investigation | CR Report | Monitoring |
Registration | Consultation Phase (CP) | Compliance Review Phase (CRP) |
Chronology and documents
Steps and milestones | Date | Remarks | Documents |
---|---|---|---|
Registry | |||
24521 Request Receipt | 2017-08-07 | Requests of a confidential nature are not published. | |
24522 Notice of Registration | 2017-08-10 | 5 business days from the date of receipt of the Request or 15 business days when further information is required from the Requesters. | |
Elegibility | |||
24523 Management Response | 2017-09-11 | 21 business days from the date of notice of registration. The response will be published as an annex to the Eligibility Memorandum. | |
24526 Eligibility due date | 2018-02-01 | 21 business days from the date of receipt of Management Response or 45 business days after the Suspension is granted. | |
24529 Eligibility Memorandum Public Disclosure | 2018-02-15 | As per the Access to Information Policy (OP-102) the disclosure of this document is done simultaneous to its distribution to the Board of Executive Directors. | |
Consultation phase | |||
Assessment | |||
24532 Deadline for Assessment | 2018-06-05 | 40 business days from the date of issuance of the eligibility memorandum. | |
24534 Assessment Report Public Disclosure | 2018-06-06 | During the Assessment, and given the specific circumstances of the Case, the Parties decided to immediately start the Consultation Phase Process. Therefore, MICI has produced a single Report for both the Assessment and Consultation Phase Process stages. Find said Report below. | |
Consultation Phase Process | |||
26656 Consideration by the Board of Executive Directors of the Consultation Phase Report | 2018-05-25 | Start date of Board consideration by short procedure. | |
26655 Consultation Phase Report Public Disclosure | 2018-06-06 | During the Assessment, and given the specific circumstances of the Case, the Parties decided to immediately start the Consultation Phase Process. Therefore, MICI has produced a single Report for both the Assessment and Consultation Phase Process stages. Disclosure of this document takes place after Board consideration. | |
Consultation Phase Closure | |||
26140 Notification to Parties | 2019-09-11 |