MICI-AR-2010-004

Argentina - Multiphase Development Infrastructure Program: Support Production in Entre Ríos

Country: Argentina

Reception date: June, 28 2010

Current Status: Closed

Requesters:
The Folonier family and neighbors of the area

Summary of the Request

Mr. Pablo Folonier and other members of his family submitted a Request to the MICI alleging potential social and environmental impacts of the construction and operation of an electrical transmission plant, one of the components of the Multiphase Development Infrastructure Program: Support Production in Entre Ríos. The Requesters claimed, among other things, lack of information; environmental misclassification of the Project; ecological risks because the plant will be located in environmentally protected areas; lack of due process for expropriation; and potential health risks due to the technology to be used at the plant.

MICI actions

Following the declaration of eligibility in the Request for the Consultation Phase, the dialogue process initiated in March of 2011, with the involvement of the Requesters, the Executing Agency and Coordinating Unit of the Project, Energia de Entre Rios SA (ENERSA) and, as observers, the Provincial Government and the IDB Project Team. 

 

The Parties reached an agreement in December of 2012, which included mitigation actions for the visual impact of the transformation station and the development of a citizen participatory plan, among others. 

 

In February of 2013, with the Consultation Phase Report already emitted, the process of monitoring the fulfillment of the agreement began. 

 

In November of 2014, the MICI carried out a field visit to verify the state of the agreement and the various activities decided upon. Practically all the agreed actions had been carried out, with the exception of the compensatory construction work, since it had become necessary for the Parties to analyze more viable alternatives that that initially agreed upon.

 

  • On November 8, 2018, MICI sent the document "Case Closure for the Multiphase Program for the Development of Production Support Infrastructure in Entre Ríos" to inform the Board of Executive Directors about the end of the MICI process.

 

With the Case Closure, MICI finalizes the case management.

 

The Case Closure document is available in the chronology section of this file.

Project Number:

AR-L1036


Environmental Category:

B


Project Name:

Multiphase Development Infrastructure: Support Production Entre Rios


Sector:

PRIVATE FIRMS AND SME DEVELOPMENT


Project Type:

Loan Operation


IDB Invest Financing:

USD 100,000,000.00


Steps and milestones Date Remarks Documents
INTAKE
Filing of Request

 

Request received by Executive Secretariat

 

 

June 28, 2010

 

 

Registration

 

Notice of registration of Request and transfer to the Consultation Phase

 

 

September 20, 2010

 

 

CONSULTATION PHASE
Eligibility for the Consultation Phase

 

Eligibility due date

 

 

October 8, 2010

(15 business days from date of transfer to the Consultation Phase)

 

 

Issuance of Eligibility Memorandum

 

 

October 8, 2010

The Eligibility Memorandum is published after it is distributed to the Board of Executive Directors.

 

Assessment

 

Assessment due date

 

 

February 8, 2011

(120 calendar days from the date of issuance of the eligibility memorandum)

 

 

Issuance of Assessment Report

 

 

April 28, 2011

The Assessment Report is published after it is distributed to the Board of Executive Directors.

 

 

Assessment Report distributed to the Board of Executive Directors

 

 

May 13, 2011

 

 

Consultation Exercise

 

Beginning of the consultation exercise

 

 

April 29, 2011

 

 

 

Issuance of Consultation Phase Report

 

 

February 6, 2013

The Consultation Phase Report is published after it is distributed to the Board of Executive Directors.

 

 

Consultation Phase Report distributed to the Board of Executive Directors

 

 

February 27, 2013

 

 

Monitoring

 

First Monitoring Report

 

 

August 30, 2013

 

 

 

Second Monitoring Report

 

 

April 21, 2014

 

 

 

Third Monitoring Report

 

 

February 13, 2015

 

 

 

Fourth Monitoring Report

 

 

March 7, 2016

 

 

 

Fifth Monitoring Report

 

 

April 10, 2017

Includes Sixth Monitoring Report: February 15, 2018.

 

Closing of the Consultation Phase

 

File transferred to the Executive Secretariat

 

November 8, 2018